Dong Nai – On May 15, Dong Nai Provincial People’s Committee just issued a document to handle difficulties and problems in the construction of Nhon Trach 3 and Nhon Trach 4 power plant projects (Phuoc Khanh commune, Nhon Trach district) and Absolutely not to obstruct the construction process in any case, strictly handle acts of hindering construction that affect the project progress.
According to the document, regarding land lease and issuance of land use rights certificates, Dong Nai Provincial People’s Committee issued Decision No. 1308/QD-UBND dated May 7, 2024 for Tin Nghia Corporation Joint Stock Company to lease land for implementation. Current infrastructure investment and business project of Ong Keo Industrial Park in Phuoc Khanh commune, Nhon Trach district.
Dong Nai assigned relevant departments to urgently focus on handling the determination of land prices to calculate land rent, sign land lease contracts and issue land use rights certificates to Tin Nghia Corporation Joint Stock Company as a basis. Sign a contract to lease land to Vietnam Petroleum Power Corporation (PV Power) according to regulations before May 25, 2024 and issue a land use right certificate to PV Power before May 31, 2024, no for delays affecting project implementation progress.
Regarding construction work on the construction site, the Management Board of Dong Nai Industrial Zones and the People’s Committee of Nhon Trach District, based on previous guiding documents of the province, absolutely do not hinder the construction process in any real estate. in any case and strictly handle acts that obstruct construction that affect project progress, and report implementation results to the Provincial People’s Committee before May 20, 2024.
For power grid projects (500kV, 220kV lines) connected to release the capacity of Nhon Trach 3 and Nhon Trach 4 power plants, on May 7, 2024, the Provincial People’s Committee submitted a report to the Provincial People’s Council to supplement the list of Land acquisition project in 2024 (second time) including the 4 power transmission projects mentioned above.
After the Provincial People’s Council passed a resolution, assigned the People’s Committee of Nhon Trach district and the People’s Committee of Long Thanh district to compile documents and register to add the project to the 2024 land use plan, as a basis for land recovery. compensation, support, and project investment site clearance according to regulations.
Nhon Trach 3 and 4 power plant projects have reached about 85% construction; The main equipment for operation has been brought to the construction site; According to the plan, Nhon Trach 3 Power Plant will generate commercial electricity in mid-November 2024.
However, the project is facing problems because there are about 30 hectares of land that have not yet signed a lease contract. In addition, the construction of the cooling water discharge channel across Road No. 4 located in Ong Keo Industrial Park also encountered problems.
Nhon Trach 3 and Nhon Trach 4 Power Plant Project located in Phuoc Khanh commune, Nhon Trach district, Dong Nai province is an important national project, PV Power is the investor. The project has a capacity of 1,500 MW and a total investment of 1.4 billion USD.
This is also the first and most modern thermal power project using imported LNG fuel in Vietnam at present. The project uses the first 1:1:1 configuration (turbine – boiler – generator) in the country and is one of the few gas turbine units with capacity (over 500MW) as well as efficiency. gas (over 60%) is the largest in the world.
Previously, on the afternoon of May 9, the State Steering Committee for important national projects and projects in the energy sector worked with Dong Nai province regarding problems with the Nhon Trach 3 and 3 power plant projects. 4.
According to news source: laodong.vn